Milestones, advance and retention · €1000.00 · 0% · 4 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €1000.00 · 0% · 4 · 5% · +3

Change the example inputs

Total agreed price€1 000.00
Advance€0.00
Total retained until release€50.00

Advance + Stage work value = €1000.00

€1000.00 × 5% → €50.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€1 000.00
1€250.00€12.50€237.50€237.50€762.50
2€250.00€12.50€237.50€475.00€525.00
3€250.00€12.50€237.50€712.50€287.50
4€250.00€12.50€237.50€950.00€50.00
7€0.00-€50.00€50.00€1 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €1000.00 · 0% · 4 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.