Milestones, advance and retention · €1000.00 · 30% · 4 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €1000.00 · 30% · 4 · 5% · +3

Change the example inputs

Total agreed price€1 000.00
Advance€300.00
Total retained until release€35.00

Advance + Stage work value = €1000.00

€700.00 × 5% → €35.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€300.00€300.00€700.00
1€175.00€8.75€166.25€466.25€533.75
2€175.00€8.75€166.25€632.50€367.50
3€175.00€8.75€166.25€798.75€201.25
4€175.00€8.75€166.25€965.00€35.00
7€0.00-€35.00€35.00€1 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €1000.00 · 30% · 4 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.