Milestones, advance and retention · €1000.00 · 30% · 6 · 15% · +3

Inspect how advances, work stages and retention change cash received in each period. €1000.00 · 30% · 6 · 15% · +3

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€1000.00
Advance€300.00
Total retained until release€105.00

Initial example inputs: Initial amount, EUR: 1000.00; Advance from price, %: 30; Number of work stages: 6; Retention on work after advance, %: 15; Periods after completion until release: 3

Change the example inputs

Total agreed price€1 000.00
Advance€300.00
Total retained until release€105.00

Advance + Stage work value = €1000.00

€700.00 × 15% → €105.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€300.00€300.00€700.00
1€116.66€17.49€99.17€399.17€600.83
2€116.66€17.49€99.17€498.34€501.66
3€116.66€17.49€99.17€597.51€402.49
4€116.66€17.49€99.17€696.68€303.32
5€116.66€17.49€99.17€795.85€204.15
6€116.70€17.55€99.15€895.00€105.00
9€0.00-€105.00€105.00€1 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €1000.00 · 30% · 6 · 15% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.