Milestones, advance and retention · €10000.00 · 0% · 8 · 15% · +0

Inspect how advances, work stages and retention change cash received in each period. €10000.00 · 0% · 8 · 15% · +0

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€10000.00
Advance€0.00
Total retained until release€1500.00

Initial example inputs: Initial amount, EUR: 10000.00; Advance from price, %: 0; Number of work stages: 8; Retention on work after advance, %: 15; Periods after completion until release: 0

Change the example inputs

Total agreed price€10 000.00
Advance€0.00
Total retained until release€1 500.00

Advance + Stage work value = €10000.00

€10000.00 × 15% → €1500.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€10 000.00
1€1 250.00€187.50€1 062.50€1 062.50€8 937.50
2€1 250.00€187.50€1 062.50€2 125.00€7 875.00
3€1 250.00€187.50€1 062.50€3 187.50€6 812.50
4€1 250.00€187.50€1 062.50€4 250.00€5 750.00
5€1 250.00€187.50€1 062.50€5 312.50€4 687.50
6€1 250.00€187.50€1 062.50€6 375.00€3 625.00
7€1 250.00€187.50€1 062.50€7 437.50€2 562.50
8€1 250.00€187.50€1 062.50€8 500.00€1 500.00
8€0.00-€1 500.00€1 500.00€10 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €10000.00 · 0% · 8 · 15% · +0

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.