SEVODOC

Milestones, advance and retention · €1500.00 · 10% · 4 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €1500.00 · 10% · 4 · 5% · +3

Change the example inputs

Total agreed price€1 500.00
Advance€150.00
Total retained until release€67.50

Advance + Stage work value = €1500.00

€1350.00 × 5% → €67.50

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€150.00€150.00€1 350.00
1€337.50€16.87€320.63€470.63€1 029.37
2€337.50€16.87€320.63€791.26€708.74
3€337.50€16.87€320.63€1 111.89€388.11
4€337.50€16.89€320.61€1 432.50€67.50
7€0.00-€67.50€67.50€1 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €1500.00 · 10% · 4 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.