Milestones, advance and retention · €1500.00 · 30% · 4 · 5% · +6

Inspect how advances, work stages and retention change cash received in each period. €1500.00 · 30% · 4 · 5% · +6

Change the example inputs

Total agreed price€1 500.00
Advance€450.00
Total retained until release€52.50

Advance + Stage work value = €1500.00

€1050.00 × 5% → €52.50

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€450.00€450.00€1 050.00
1€262.50€13.12€249.38€699.38€800.62
2€262.50€13.12€249.38€948.76€551.24
3€262.50€13.12€249.38€1 198.14€301.86
4€262.50€13.14€249.36€1 447.50€52.50
10€0.00-€52.50€52.50€1 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €1500.00 · 30% · 4 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.