SEVODOC

Milestones, advance and retention · €1500.00 · 50% · 3 · 10% · +6

Inspect how advances, work stages and retention change cash received in each period. €1500.00 · 50% · 3 · 10% · +6

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€1500.00
Advance€750.00
Total retained until release€75.00

Initial example inputs: Initial amount, EUR: 1500.00; Advance from price, %: 50; Number of work stages: 3; Retention on work after advance, %: 10; Periods after completion until release: 6

Change the example inputs

Total agreed price€1 500.00
Advance€750.00
Total retained until release€75.00

Advance + Stage work value = €1500.00

€750.00 × 10% → €75.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€750.00€750.00€750.00
1€250.00€25.00€225.00€975.00€525.00
2€250.00€25.00€225.00€1 200.00€300.00
3€250.00€25.00€225.00€1 425.00€75.00
9€0.00-€75.00€75.00€1 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €1500.00 · 50% · 3 · 10% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.