SEVODOC

Milestones, advance and retention · €2000.00 · 0% · 2 · 15% · +3

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 0% · 2 · 15% · +3

Change the example inputs

Total agreed price€2 000.00
Advance€0.00
Total retained until release€300.00

Advance + Stage work value = €2000.00

€2000.00 × 15% → €300.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€2 000.00
1€1 000.00€150.00€850.00€850.00€1 150.00
2€1 000.00€150.00€850.00€1 700.00€300.00
5€0.00-€300.00€300.00€2 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 0% · 2 · 15% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.