SEVODOC

Milestones, advance and retention · €2000.00 · 10% · 6 · 15% · +3

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 10% · 6 · 15% · +3

Change the example inputs

Total agreed price€2 000.00
Advance€200.00
Total retained until release€270.00

Advance + Stage work value = €2000.00

€1800.00 × 15% → €270.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€200.00€200.00€1 800.00
1€300.00€45.00€255.00€455.00€1 545.00
2€300.00€45.00€255.00€710.00€1 290.00
3€300.00€45.00€255.00€965.00€1 035.00
4€300.00€45.00€255.00€1 220.00€780.00
5€300.00€45.00€255.00€1 475.00€525.00
6€300.00€45.00€255.00€1 730.00€270.00
9€0.00-€270.00€270.00€2 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 10% · 6 · 15% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.