Milestones, advance and retention · €2000.00 · 20% · 6 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 20% · 6 · 5% · +3

Change the example inputs

Total agreed price€2 000.00
Advance€400.00
Total retained until release€80.00

Advance + Stage work value = €2000.00

€1600.00 × 5% → €80.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€400.00€400.00€1 600.00
1€266.66€13.33€253.33€653.33€1 346.67
2€266.66€13.33€253.33€906.66€1 093.34
3€266.66€13.33€253.33€1 159.99€840.01
4€266.66€13.33€253.33€1 413.32€586.68
5€266.66€13.33€253.33€1 666.65€333.35
6€266.70€13.35€253.35€1 920.00€80.00
9€0.00-€80.00€80.00€2 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 20% · 6 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.