SEVODOC

Milestones, advance and retention · €2000.00 · 30% · 3 · 15% · +6

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 30% · 3 · 15% · +6

Change the example inputs

Total agreed price€2 000.00
Advance€600.00
Total retained until release€210.00

Advance + Stage work value = €2000.00

€1400.00 × 15% → €210.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€600.00€600.00€1 400.00
1€466.66€69.99€396.67€996.67€1 003.33
2€466.66€69.99€396.67€1 393.34€606.66
3€466.68€70.02€396.66€1 790.00€210.00
9€0.00-€210.00€210.00€2 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 30% · 3 · 15% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.