SEVODOC

Milestones, advance and retention · €2000.00 · 30% · 6 · 5% · +6

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 30% · 6 · 5% · +6

Change the example inputs

Total agreed price€2 000.00
Advance€600.00
Total retained until release€70.00

Advance + Stage work value = €2000.00

€1400.00 × 5% → €70.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€600.00€600.00€1 400.00
1€233.33€11.66€221.67€821.67€1 178.33
2€233.33€11.66€221.67€1 043.34€956.66
3€233.33€11.66€221.67€1 265.01€734.99
4€233.33€11.66€221.67€1 486.68€513.32
5€233.33€11.66€221.67€1 708.35€291.65
6€233.35€11.70€221.65€1 930.00€70.00
12€0.00-€70.00€70.00€2 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2000.00 · 30% · 6 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.