SEVODOC

Milestones, advance and retention · €20000.00 · 10% · 3 · 5% · +6

Inspect how advances, work stages and retention change cash received in each period. €20000.00 · 10% · 3 · 5% · +6

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€20000.00
Advance€2000.00
Total retained until release€900.00

Initial example inputs: Initial amount, EUR: 20000.00; Advance from price, %: 10; Number of work stages: 3; Retention on work after advance, %: 5; Periods after completion until release: 6

Change the example inputs

Total agreed price€20 000.00
Advance€2 000.00
Total retained until release€900.00

Advance + Stage work value = €20000.00

€18000.00 × 5% → €900.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€2 000.00€2 000.00€18 000.00
1€6 000.00€300.00€5 700.00€7 700.00€12 300.00
2€6 000.00€300.00€5 700.00€13 400.00€6 600.00
3€6 000.00€300.00€5 700.00€19 100.00€900.00
9€0.00-€900.00€900.00€20 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €20000.00 · 10% · 3 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.