Milestones, advance and retention · €20000.00 · 30% · 2 · 10% · +0

Inspect how advances, work stages and retention change cash received in each period. €20000.00 · 30% · 2 · 10% · +0

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€20000.00
Advance€6000.00
Total retained until release€1400.00

Initial example inputs: Initial amount, EUR: 20000.00; Advance from price, %: 30; Number of work stages: 2; Retention on work after advance, %: 10; Periods after completion until release: 0

Change the example inputs

Total agreed price€20 000.00
Advance€6 000.00
Total retained until release€1 400.00

Advance + Stage work value = €20000.00

€14000.00 × 10% → €1400.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€6 000.00€6 000.00€14 000.00
1€7 000.00€700.00€6 300.00€12 300.00€7 700.00
2€7 000.00€700.00€6 300.00€18 600.00€1 400.00
2€0.00-€1 400.00€1 400.00€20 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €20000.00 · 30% · 2 · 10% · +0

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.