Milestones, advance and retention · €2500.00 · 0% · 3 · 15% · +1

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 0% · 3 · 15% · +1

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€2500.00
Advance€0.00
Total retained until release€375.00

Initial example inputs: Initial amount, EUR: 2500.00; Advance from price, %: 0; Number of work stages: 3; Retention on work after advance, %: 15; Periods after completion until release: 1

Change the example inputs

Total agreed price€2 500.00
Advance€0.00
Total retained until release€375.00

Advance + Stage work value = €2500.00

€2500.00 × 15% → €375.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€2 500.00
1€833.33€124.99€708.34€708.34€1 791.66
2€833.33€124.99€708.34€1 416.68€1 083.32
3€833.34€125.02€708.32€2 125.00€375.00
4€0.00-€375.00€375.00€2 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 0% · 3 · 15% · +1

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.