Milestones, advance and retention · €2500.00 · 10% · 6 · 15% · +1

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 10% · 6 · 15% · +1

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€2500.00
Advance€250.00
Total retained until release€337.50

Initial example inputs: Initial amount, EUR: 2500.00; Advance from price, %: 10; Number of work stages: 6; Retention on work after advance, %: 15; Periods after completion until release: 1

Change the example inputs

Total agreed price€2 500.00
Advance€250.00
Total retained until release€337.50

Advance + Stage work value = €2500.00

€2250.00 × 15% → €337.50

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€250.00€250.00€2 250.00
1€375.00€56.25€318.75€568.75€1 931.25
2€375.00€56.25€318.75€887.50€1 612.50
3€375.00€56.25€318.75€1 206.25€1 293.75
4€375.00€56.25€318.75€1 525.00€975.00
5€375.00€56.25€318.75€1 843.75€656.25
6€375.00€56.25€318.75€2 162.50€337.50
7€0.00-€337.50€337.50€2 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 10% · 6 · 15% · +1

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.