SEVODOC

Milestones, advance and retention · €2500.00 · 20% · 4 · 10% · +3

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 20% · 4 · 10% · +3

Change the example inputs

Total agreed price€2 500.00
Advance€500.00
Total retained until release€200.00

Advance + Stage work value = €2500.00

€2000.00 × 10% → €200.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€500.00€500.00€2 000.00
1€500.00€50.00€450.00€950.00€1 550.00
2€500.00€50.00€450.00€1 400.00€1 100.00
3€500.00€50.00€450.00€1 850.00€650.00
4€500.00€50.00€450.00€2 300.00€200.00
7€0.00-€200.00€200.00€2 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 20% · 4 · 10% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.