SEVODOC

Milestones, advance and retention · €2500.00 · 30% · 3 · 5% · +1

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 30% · 3 · 5% · +1

Change the example inputs

Total agreed price€2 500.00
Advance€750.00
Total retained until release€87.50

Advance + Stage work value = €2500.00

€1750.00 × 5% → €87.50

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€750.00€750.00€1 750.00
1€583.33€29.16€554.17€1 304.17€1 195.83
2€583.33€29.16€554.17€1 858.34€641.66
3€583.34€29.18€554.16€2 412.50€87.50
4€0.00-€87.50€87.50€2 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 30% · 3 · 5% · +1

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.