SEVODOC

Milestones, advance and retention · €2500.00 · 30% · 4 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 30% · 4 · 5% · +3

Change the example inputs

Total agreed price€2 500.00
Advance€750.00
Total retained until release€87.50

Advance + Stage work value = €2500.00

€1750.00 × 5% → €87.50

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€750.00€750.00€1 750.00
1€437.50€21.87€415.63€1 165.63€1 334.37
2€437.50€21.87€415.63€1 581.26€918.74
3€437.50€21.87€415.63€1 996.89€503.11
4€437.50€21.89€415.61€2 412.50€87.50
7€0.00-€87.50€87.50€2 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €2500.00 · 30% · 4 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.