Milestones, advance and retention · €25000.00 · 10% · 2 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €25000.00 · 10% · 2 · 5% · +3

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€25000.00
Advance€2500.00
Total retained until release€1125.00

Initial example inputs: Initial amount, EUR: 25000.00; Advance from price, %: 10; Number of work stages: 2; Retention on work after advance, %: 5; Periods after completion until release: 3

Change the example inputs

Total agreed price€25 000.00
Advance€2 500.00
Total retained until release€1 125.00

Advance + Stage work value = €25000.00

€22500.00 × 5% → €1125.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€2 500.00€2 500.00€22 500.00
1€11 250.00€562.50€10 687.50€13 187.50€11 812.50
2€11 250.00€562.50€10 687.50€23 875.00€1 125.00
5€0.00-€1 125.00€1 125.00€25 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €25000.00 · 10% · 2 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.