SEVODOC

Milestones, advance and retention · €25000.00 · 50% · 3 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €25000.00 · 50% · 3 · 5% · +3

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€25000.00
Advance€12500.00
Total retained until release€625.00

Initial example inputs: Initial amount, EUR: 25000.00; Advance from price, %: 50; Number of work stages: 3; Retention on work after advance, %: 5; Periods after completion until release: 3

Change the example inputs

Total agreed price€25 000.00
Advance€12 500.00
Total retained until release€625.00

Advance + Stage work value = €25000.00

€12500.00 × 5% → €625.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€12 500.00€12 500.00€12 500.00
1€4 166.66€208.33€3 958.33€16 458.33€8 541.67
2€4 166.66€208.33€3 958.33€20 416.66€4 583.34
3€4 166.68€208.34€3 958.34€24 375.00€625.00
6€0.00-€625.00€625.00€25 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €25000.00 · 50% · 3 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.