SEVODOC

Milestones, advance and retention · €3000.00 · 0% · 4 · 5% · +6

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 0% · 4 · 5% · +6

Change the example inputs

Total agreed price€3 000.00
Advance€0.00
Total retained until release€150.00

Advance + Stage work value = €3000.00

€3000.00 × 5% → €150.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€3 000.00
1€750.00€37.50€712.50€712.50€2 287.50
2€750.00€37.50€712.50€1 425.00€1 575.00
3€750.00€37.50€712.50€2 137.50€862.50
4€750.00€37.50€712.50€2 850.00€150.00
10€0.00-€150.00€150.00€3 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 0% · 4 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.