Milestones, advance and retention · €3000.00 · 0% · 8 · 5% · +0

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 0% · 8 · 5% · +0

Change the example inputs

Total agreed price€3 000.00
Advance€0.00
Total retained until release€150.00

Advance + Stage work value = €3000.00

€3000.00 × 5% → €150.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€3 000.00
1€375.00€18.75€356.25€356.25€2 643.75
2€375.00€18.75€356.25€712.50€2 287.50
3€375.00€18.75€356.25€1 068.75€1 931.25
4€375.00€18.75€356.25€1 425.00€1 575.00
5€375.00€18.75€356.25€1 781.25€1 218.75
6€375.00€18.75€356.25€2 137.50€862.50
7€375.00€18.75€356.25€2 493.75€506.25
8€375.00€18.75€356.25€2 850.00€150.00
8€0.00-€150.00€150.00€3 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 0% · 8 · 5% · +0

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.