Milestones, advance and retention · €3000.00 · 10% · 4 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 10% · 4 · 5% · +3

Change the example inputs

Total agreed price€3 000.00
Advance€300.00
Total retained until release€135.00

Advance + Stage work value = €3000.00

€2700.00 × 5% → €135.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€300.00€300.00€2 700.00
1€675.00€33.75€641.25€941.25€2 058.75
2€675.00€33.75€641.25€1 582.50€1 417.50
3€675.00€33.75€641.25€2 223.75€776.25
4€675.00€33.75€641.25€2 865.00€135.00
7€0.00-€135.00€135.00€3 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 10% · 4 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.