SEVODOC

Milestones, advance and retention · €3000.00 · 20% · 4 · 5% · +1

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 20% · 4 · 5% · +1

Change the example inputs

Total agreed price€3 000.00
Advance€600.00
Total retained until release€120.00

Advance + Stage work value = €3000.00

€2400.00 × 5% → €120.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€600.00€600.00€2 400.00
1€600.00€30.00€570.00€1 170.00€1 830.00
2€600.00€30.00€570.00€1 740.00€1 260.00
3€600.00€30.00€570.00€2 310.00€690.00
4€600.00€30.00€570.00€2 880.00€120.00
5€0.00-€120.00€120.00€3 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 20% · 4 · 5% · +1

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.