Total agreed price€3 000.00
Advance€600.00
Total retained until release€240.00

Advance + Stage work value = €3000.00

€2400.00 × 10% → €240.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€600.00€600.00€2 400.00
1€300.00€30.00€270.00€870.00€2 130.00
2€300.00€30.00€270.00€1 140.00€1 860.00
3€300.00€30.00€270.00€1 410.00€1 590.00
4€300.00€30.00€270.00€1 680.00€1 320.00
5€300.00€30.00€270.00€1 950.00€1 050.00
6€300.00€30.00€270.00€2 220.00€780.00
7€300.00€30.00€270.00€2 490.00€510.00
8€300.00€30.00€270.00€2 760.00€240.00
11€0.00-€240.00€240.00€3 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €3000.00 · 20% · 8 · 10% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.