SEVODOC

Milestones, advance and retention · €30000.00 · 50% · 2 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €30000.00 · 50% · 2 · 5% · +3

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€30000.00
Advance€15000.00
Total retained until release€750.00

Initial example inputs: Initial amount, EUR: 30000.00; Advance from price, %: 50; Number of work stages: 2; Retention on work after advance, %: 5; Periods after completion until release: 3

Change the example inputs

Total agreed price€30 000.00
Advance€15 000.00
Total retained until release€750.00

Advance + Stage work value = €30000.00

€15000.00 × 5% → €750.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€15 000.00€15 000.00€15 000.00
1€7 500.00€375.00€7 125.00€22 125.00€7 875.00
2€7 500.00€375.00€7 125.00€29 250.00€750.00
5€0.00-€750.00€750.00€30 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €30000.00 · 50% · 2 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.