Milestones, advance and retention · €4000.00 · 0% · 2 · 5% · +6

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 0% · 2 · 5% · +6

Change the example inputs

Total agreed price€4 000.00
Advance€0.00
Total retained until release€200.00

Advance + Stage work value = €4000.00

€4000.00 × 5% → €200.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€4 000.00
1€2 000.00€100.00€1 900.00€1 900.00€2 100.00
2€2 000.00€100.00€1 900.00€3 800.00€200.00
8€0.00-€200.00€200.00€4 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 0% · 2 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.