Milestones, advance and retention · €4000.00 · 30% · 2 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 30% · 2 · 5% · +3

Change the example inputs

Total agreed price€4 000.00
Advance€1 200.00
Total retained until release€140.00

Advance + Stage work value = €4000.00

€2800.00 × 5% → €140.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€1 200.00€1 200.00€2 800.00
1€1 400.00€70.00€1 330.00€2 530.00€1 470.00
2€1 400.00€70.00€1 330.00€3 860.00€140.00
5€0.00-€140.00€140.00€4 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 30% · 2 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.