Milestones, advance and retention · €500.00 · 20% · 3 · 5% · +6

Inspect how advances, work stages and retention change cash received in each period. €500.00 · 20% · 3 · 5% · +6

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€500.00
Advance€100.00
Total retained until release€20.00

Initial example inputs: Initial amount, EUR: 500.00; Advance from price, %: 20; Number of work stages: 3; Retention on work after advance, %: 5; Periods after completion until release: 6

Change the example inputs

Total agreed price€500.00
Advance€100.00
Total retained until release€20.00

Advance + Stage work value = €500.00

€400.00 × 5% → €20.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€100.00€100.00€400.00
1€133.33€6.66€126.67€226.67€273.33
2€133.33€6.66€126.67€353.34€146.66
3€133.34€6.68€126.66€480.00€20.00
9€0.00-€20.00€20.00€500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €500.00 · 20% · 3 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.