SEVODOC

Milestones, advance and retention · €500.00 · 50% · 8 · 5% · +6

Inspect how advances, work stages and retention change cash received in each period. €500.00 · 50% · 8 · 5% · +6

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€500.00
Advance€250.00
Total retained until release€12.50

Initial example inputs: Initial amount, EUR: 500.00; Advance from price, %: 50; Number of work stages: 8; Retention on work after advance, %: 5; Periods after completion until release: 6

Change the example inputs

Total agreed price€500.00
Advance€250.00
Total retained until release€12.50

Advance + Stage work value = €500.00

€250.00 × 5% → €12.50

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€250.00€250.00€250.00
1€31.25€1.56€29.69€279.69€220.31
2€31.25€1.56€29.69€309.38€190.62
3€31.25€1.56€29.69€339.07€160.93
4€31.25€1.56€29.69€368.76€131.24
5€31.25€1.56€29.69€398.45€101.55
6€31.25€1.56€29.69€428.14€71.86
7€31.25€1.56€29.69€457.83€42.17
8€31.25€1.58€29.67€487.50€12.50
14€0.00-€12.50€12.50€500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €500.00 · 50% · 8 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.