Total agreed price€5 000.00
Advance€0.00
Total retained until release€500.00

Advance + Stage work value = €5000.00

€5000.00 × 10% → €500.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€5 000.00
1€1 250.00€125.00€1 125.00€1 125.00€3 875.00
2€1 250.00€125.00€1 125.00€2 250.00€2 750.00
3€1 250.00€125.00€1 125.00€3 375.00€1 625.00
4€1 250.00€125.00€1 125.00€4 500.00€500.00
10€0.00-€500.00€500.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 0% · 4 · 10% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.