SEVODOC

Milestones, advance and retention · €5000.00 · 0% · 6 · 15% · +3

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 0% · 6 · 15% · +3

Change the example inputs

Total agreed price€5 000.00
Advance€0.00
Total retained until release€750.00

Advance + Stage work value = €5000.00

€5000.00 × 15% → €750.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€5 000.00
1€833.33€124.99€708.34€708.34€4 291.66
2€833.33€124.99€708.34€1 416.68€3 583.32
3€833.33€124.99€708.34€2 125.02€2 874.98
4€833.33€124.99€708.34€2 833.36€2 166.64
5€833.33€124.99€708.34€3 541.70€1 458.30
6€833.35€125.05€708.30€4 250.00€750.00
9€0.00-€750.00€750.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 0% · 6 · 15% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.