Milestones, advance and retention · €5000.00 · 0% · 6 · 5% · +0

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 0% · 6 · 5% · +0

Change the example inputs

Total agreed price€5 000.00
Advance€0.00
Total retained until release€250.00

Advance + Stage work value = €5000.00

€5000.00 × 5% → €250.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€0.00€0.00€5 000.00
1€833.33€41.66€791.67€791.67€4 208.33
2€833.33€41.66€791.67€1 583.34€3 416.66
3€833.33€41.66€791.67€2 375.01€2 624.99
4€833.33€41.66€791.67€3 166.68€1 833.32
5€833.33€41.66€791.67€3 958.35€1 041.65
6€833.35€41.70€791.65€4 750.00€250.00
6€0.00-€250.00€250.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 0% · 6 · 5% · +0

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.