Milestones, advance and retention · €5000.00 · 20% · 3 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 20% · 3 · 5% · +3

Change the example inputs

Total agreed price€5 000.00
Advance€1 000.00
Total retained until release€200.00

Advance + Stage work value = €5000.00

€4000.00 × 5% → €200.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€1 000.00€1 000.00€4 000.00
1€1 333.33€66.66€1 266.67€2 266.67€2 733.33
2€1 333.33€66.66€1 266.67€3 533.34€1 466.66
3€1 333.34€66.68€1 266.66€4 800.00€200.00
6€0.00-€200.00€200.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 20% · 3 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.