Milestones, advance and retention · €5000.00 · 20% · 4 · 15% · +6

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 20% · 4 · 15% · +6

Change the example inputs

Total agreed price€5 000.00
Advance€1 000.00
Total retained until release€600.00

Advance + Stage work value = €5000.00

€4000.00 × 15% → €600.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€1 000.00€1 000.00€4 000.00
1€1 000.00€150.00€850.00€1 850.00€3 150.00
2€1 000.00€150.00€850.00€2 700.00€2 300.00
3€1 000.00€150.00€850.00€3 550.00€1 450.00
4€1 000.00€150.00€850.00€4 400.00€600.00
10€0.00-€600.00€600.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 20% · 4 · 15% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.