SEVODOC

Milestones, advance and retention · €5000.00 · 50% · 2 · 15% · +3

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 50% · 2 · 15% · +3

Change the example inputs

Total agreed price€5 000.00
Advance€2 500.00
Total retained until release€375.00

Advance + Stage work value = €5000.00

€2500.00 × 15% → €375.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€2 500.00€2 500.00€2 500.00
1€1 250.00€187.50€1 062.50€3 562.50€1 437.50
2€1 250.00€187.50€1 062.50€4 625.00€375.00
5€0.00-€375.00€375.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 50% · 2 · 15% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.