Total agreed price€5 000.00
Advance€2 500.00
Total retained until release€125.00

Advance + Stage work value = €5000.00

€2500.00 × 5% → €125.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€2 500.00€2 500.00€2 500.00
1€416.66€20.83€395.83€2 895.83€2 104.17
2€416.66€20.83€395.83€3 291.66€1 708.34
3€416.66€20.83€395.83€3 687.49€1 312.51
4€416.66€20.83€395.83€4 083.32€916.68
5€416.66€20.83€395.83€4 479.15€520.85
6€416.70€20.85€395.85€4 875.00€125.00
12€0.00-€125.00€125.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 50% · 6 · 5% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.