SEVODOC

Milestones, advance and retention · €750.00 · 20% · 4 · 10% · +6

Inspect how advances, work stages and retention change cash received in each period. €750.00 · 20% · 4 · 10% · +6

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€750.00
Advance€150.00
Total retained until release€60.00

Initial example inputs: Initial amount, EUR: 750.00; Advance from price, %: 20; Number of work stages: 4; Retention on work after advance, %: 10; Periods after completion until release: 6

Change the example inputs

Total agreed price€750.00
Advance€150.00
Total retained until release€60.00

Advance + Stage work value = €750.00

€600.00 × 10% → €60.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€150.00€150.00€600.00
1€150.00€15.00€135.00€285.00€465.00
2€150.00€15.00€135.00€420.00€330.00
3€150.00€15.00€135.00€555.00€195.00
4€150.00€15.00€135.00€690.00€60.00
10€0.00-€60.00€60.00€750.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €750.00 · 20% · 4 · 10% · +6

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.