SEVODOC

Milestones, advance and retention · €7500.00 · 30% · 4 · 5% · +3

Inspect how advances, work stages and retention change cash received in each period. €7500.00 · 30% · 4 · 5% · +3

Change the example inputs

Total agreed price€7 500.00
Advance€2 250.00
Total retained until release€262.50

Advance + Stage work value = €7500.00

€5250.00 × 5% → €262.50

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€2 250.00€2 250.00€5 250.00
1€1 312.50€65.62€1 246.88€3 496.88€4 003.12
2€1 312.50€65.62€1 246.88€4 743.76€2 756.24
3€1 312.50€65.62€1 246.88€5 990.64€1 509.36
4€1 312.50€65.64€1 246.86€7 237.50€262.50
7€0.00-€262.50€262.50€7 500.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €7500.00 · 30% · 4 · 5% · +3

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.