Milestones, advance and retention · €4000.00 · 20% · 4 · 15% · +1

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 20% · 4 · 15% · +1

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€4000.00
Advance€800.00
Total retained until release€480.00

Initial example inputs: Initial amount, EUR: 4000.00; Advance from price, %: 20; Number of work stages: 4; Retention on work after advance, %: 15; Periods after completion until release: 1

Change the example inputs

Total agreed price€4 000.00
Advance€800.00
Total retained until release€480.00

Advance + Stage work value = €4000.00

€3200.00 × 15% → €480.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€800.00€800.00€3 200.00
1€800.00€120.00€680.00€1 480.00€2 520.00
2€800.00€120.00€680.00€2 160.00€1 840.00
3€800.00€120.00€680.00€2 840.00€1 160.00
4€800.00€120.00€680.00€3 520.00€480.00
5€0.00-€480.00€480.00€4 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 20% · 4 · 15% · +1

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.