SEVODOC

Milestones, advance and retention · €4000.00 · 20% · 6 · 5% · +0

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 20% · 6 · 5% · +0

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€4000.00
Advance€800.00
Total retained until release€160.00

Initial example inputs: Initial amount, EUR: 4000.00; Advance from price, %: 20; Number of work stages: 6; Retention on work after advance, %: 5; Periods after completion until release: 0

Change the example inputs

Total agreed price€4 000.00
Advance€800.00
Total retained until release€160.00

Advance + Stage work value = €4000.00

€3200.00 × 5% → €160.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€800.00€800.00€3 200.00
1€533.33€26.66€506.67€1 306.67€2 693.33
2€533.33€26.66€506.67€1 813.34€2 186.66
3€533.33€26.66€506.67€2 320.01€1 679.99
4€533.33€26.66€506.67€2 826.68€1 173.32
5€533.33€26.66€506.67€3 333.35€666.65
6€533.35€26.70€506.65€3 840.00€160.00
6€0.00-€160.00€160.00€4 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €4000.00 · 20% · 6 · 5% · +0

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.