Milestones, advance and retention · €5000.00 · 50% · 8 · 10% · +0

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 50% · 8 · 10% · +0

This task at a glance

Initial example result
What to clarifyExample or option on this page
Total agreed price€5000.00
Advance€2500.00
Total retained until release€250.00

Initial example inputs: Initial amount, EUR: 5000.00; Advance from price, %: 50; Number of work stages: 8; Retention on work after advance, %: 10; Periods after completion until release: 0

Change the example inputs

Total agreed price€5 000.00
Advance€2 500.00
Total retained until release€250.00

Advance + Stage work value = €5000.00

€2500.00 × 10% → €250.00

Checkable payment schedule
PeriodStage work valueRetained / releasedCash paymentCumulative paidRemaining balance
0€0.00€0.00€2 500.00€2 500.00€2 500.00
1€312.50€31.25€281.25€2 781.25€2 218.75
2€312.50€31.25€281.25€3 062.50€1 937.50
3€312.50€31.25€281.25€3 343.75€1 656.25
4€312.50€31.25€281.25€3 625.00€1 375.00
5€312.50€31.25€281.25€3 906.25€1 093.75
6€312.50€31.25€281.25€4 187.50€812.50
7€312.50€31.25€281.25€4 468.75€531.25
8€312.50€31.25€281.25€4 750.00€250.00
8€0.00-€250.00€250.00€5 000.00€0.00

The calculation is a local example. This action saves no customer document and makes no payment.

Example assumptions and limits

Continue in the actual tool

Common questions

What can I verify in this example?

Inspect how advances, work stages and retention change cash received in each period. €5000.00 · 50% · 8 · 10% · +0

Which assumptions should I change for my transaction?

Retention is an assumed contractual percentage of work after the advance. The release row assumes agreed conditions are met; it is not evidence of an actual release.

Will opening a template produce an approved document?

Hypothetical calculation. It does not save a document, prove payment or post a journal entry.